Seagreen Offshore Wind Farm’s costs per MWh are higher than the current Strike Price per MWh.
How will this compare with an Advanced Nuclear Power Plant (NPP)?
4 min readSep 27, 2020

Seagreen Offshore Wind Farm is a SSE project. The Website tells us the 1075 MW of installed Wind Turbine Generators (WTGs) will power 1.3 million homes, for which the current BEIS usage figure is 3,618 kWh per year, per home.
This works out at an annual generation of >4.7 million MWh per year which, over the 25 years lifespan, will supply 117.7 million MWh of intermittent electricity to the National Grid.
One of several reports describe Seagreen as “…an offshore wind farm that may cost more than £5.7 billion to develop and operate…”. Presumably, this figure covers the £3.0 billion of capital investment to get to the point of operation, plus O & M, plus decommissioning and waste disposal.
£5.7 billion divided by 117.7 million MWh works out at a Total Cost of £48.43/MWh.
But here’s the thing: Seagreen’s bid for a CfD contract settled at a price which is currently £48.09/MWh; by the time operation starts in 2025, linked to the CPI, that price might reach £53.00/MWh.
For the past 10 years, the Wholesale electricity price has hovered around the £50.00/MWh mark. So maybe by 2025, Seagreen can count on an average £60.00/MWh over its lifespan to 2050.
Per MWh, the income (£60.00) less the costs (£48.43) results in ‘profits’ of £11.57. Applied to 117.7 million MWh produces a total of £1.36 billion of ‘profit’.
Every £1.00 of capital invested yields a ‘profit’ of £0.45
— — — — — — // — — — — — —

— — — — — — // — — — — — —
So how does investing £3.0 billion in an Advanced NPP compare?

The Rolls- Royce Consortium will build factories in 2021, to start producing components for the first NPP to commence build in 2025 (Part 3) with a build programme of 4 years (Part 7). The commercial operation target date is 2029.
Within 2 or 3 years, at a capital investment rate of £1.8 billion for 440 MW, £3.0 billion of capital investment would ‘procure’ 733 MW of installed capacity.
From, say 2035, a capacity of 733 MW of would generate 5.8 million MWh each year and a total of 346.7 million MWh over the 60 years lifespan. The £3.0 billion of capital cost over 346.7 million MWh gives a capital cost content of £8.65/MWh.